The Government Just Told You to Stop. Now What?
A stop-work order can freeze your contract overnight, and what you do in the first few days decides whether you get paid for the disruption…

Published 2026 | TIKC NewsWire
You are in the middle of performing a contract when an email lands from the contracting officer: stop work immediately. No explanation you can argue with, no warning. It is called a stop-work order, and the government has the right to issue one. Maybe funding is in question, maybe priorities shifted, maybe there is a protest on a related award. Whatever the reason, your contract just froze. What you do in the next few days decides whether this becomes a manageable pause or a loss you absorb out of your own pocket.
What a stop-work order actually is
A stop-work order is a written direction from the contracting officer to halt all or part of the work for a set period. It is not a termination and it is not a punishment. The government uses it to buy time while it sorts something out. Importantly, the clause that lets the government stop you also promises that if the stop was not your fault, you can recover the costs the delay caused and get your schedule adjusted. The protection is real, but only if you handle the pause correctly.
The first 48 hours matter most
When the order hits, your instinct might be to keep a few people working to stay on track. Do not. A stop-work order means stop, and continuing to incur costs after it can mean you eat those costs yourself. Instead, stop the work the order covers, and then immediately start protecting your position: document the date and time you received it, record where the work stood, and capture the costs the stoppage is creating, like idle employees, equipment you cannot redeploy, and commitments you cannot cancel.
How the pause ends
A stop-work order does not last forever. Within the period set, the government has to do one of two things: tell you to resume, or convert the stop into a termination. If it tells you to resume, you are entitled to an adjustment for the delay and added costs. If it converts to a termination, your recovery shifts to the termination settlement process instead. Either way, the records you kept during the freeze are what turn your disruption into dollars you can actually claim.
What to do now
- Stop when told. Halt the work the order covers right away, and do not keep incurring costs on it.
- Timestamp everything. Record exactly when you got the order and what the work status was at that moment.
- Track your delay costs. Capture idle labor, stranded equipment, and commitments you cannot cancel during the pause.
- Keep talking to the CO. Stay in contact so you know whether a resume or a termination is coming.
- Prepare your adjustment. When work resumes, be ready to request the time and cost adjustment the clause allows.
A stop-work order feels like being punished for something you did not do. It does not have to cost you. The clause exists to make you whole for a delay the government caused, and the contractors who recover are the ones who stop cleanly and document everything from the first hour. Freeze the work, protect your records, and claim your adjustment, and the pause becomes a line item instead of a loss. Brick by brick.
FAQ
Can the government really make me stop with no notice?
Yes. The stop-work clause in your contract gives the contracting officer the right to direct you to halt work for a defined period. It is not a breach, but it does come with the promise of a fair adjustment if the stop was not your fault.
Will I get paid for the downtime?
Generally you can recover the added costs the stoppage caused and get your schedule extended, as long as you stopped as directed and documented the impact. Costs you incur by ignoring the order are usually on you.
How long can a stop-work order last?
It runs for the period stated in the order. Within that time the government must either tell you to resume or terminate the affected work, so the freeze is temporary by design.
What if it turns into a termination?
If the government converts the stop-work order into a termination, your recovery moves into the termination settlement process, where you document completed work and incurred costs to be paid fairly.
Sources
Federal Acquisition Regulation. (2026). 52.242-15, Stop-Work Order.
Federal Acquisition Regulation. (2026). Subpart 42.13, Suspension of Work, Stop-Work Orders, and Government Delay of Work.
This article is general information, not legal advice.
About the Author
TIKC Staff Writer
Team Integrity Knowledge Center is a GovCon education and consulting platform helping small, women-owned, and minority-owned businesses win and keep federal and state contracts with plain-English guidance. Build, grow, scale, brick by brick. Contact
Your next step
Talk it through with a TIKC advisor
Continue reading
Related stories

When Your Costs Rise Mid-Contract: Economic Price Adjustment Clauses
A fixed-price contract can turn into a money-loser when material costs spike. An Economic Price Adjustment clause is the built-in tool that lets your price…

Personal Services and the Line a Contractor Cannot Cross
A contract can be legal to win but illegal to perform if the government ends up supervising your people like employees, or if you start…

Doing Extra Work for Free? The Changes Clause and Getting Paid for It
The government can direct you to change the work mid-contract, and sometimes it changes the work without ever saying so. The Changes Clause entitles you…

Your Invoice Is a Legal Claim: Getting WAWF Right
On most defense contracts you bill through an electronic system called WAWF, and every invoice you submit is a formal claim for payment. A sloppy…
SBIR Data Rights: The Protection Most Small Innovators Give Away by Accident
If you win an SBIR or STTR award, the research you create comes with special data-rights protection the government does not get with most contracts…

A $29.5 Million Reminder That Your Certifications Have to Be True
A major defense contractor just agreed to pay $29.5 million over allegations that it certified compliance with federal rules it was not actually following. The…
After a Merger, Are You Still a Small Business? The Recertification Rule
A merger or acquisition can cost you your small-business status overnight, and the rules make you report it. Keep running set-aside work as if nothing…

Technical Data Rights: How to Keep the Government From Giving Your Designs to a Competitor
When you deliver drawings, software, or technical data to the government, the markings you put on them decide who else can use them. Mark them…

Selling Your Company? The Government Has to Agree to Keep Your Contract
You cannot simply hand your federal contract to a buyer the way you would transfer a commercial deal. The government has to approve the transfer…

Earned Value Reporting: When Your Progress Numbers Become a Legal Statement
On big contracts you report how much work you have earned, not just how much you spent. Inflate that number to look on track and…

Expressly Unallowable Costs: When Billing the Wrong Expense Comes With a Penalty
Some costs are not just disallowed when you bill them to the government. They carry an automatic penalty on top, sometimes double. Here is what…